U.S. v. Shaw, (10th Cir. 2005)

Federal Circuits

Linked as:

Text




UNITED

STATES COURT OF APPEALS

TENTH CIRCUIT

UNITED STATES OF AMERICA,

Plaintiff - Appellant,

v.

EDWARD A. SHAW,

Defendant - Appellee.

Nos. 01-3344 & 01-3310

(D. Kansas)

(D.Ct. No. 99-CR-10081-01-JMT)

ORDER AND JUDGMENT(*)

Before TACHA, ANDERSON, and O'BRIEN,

Circuit Judges.

Edward Shaw was convicted by a jury of knowingly engaging in a scheme

to falsify, conceal or cover up the presence of asbestos at the Shallow Water

Refinery, in violation of 18 U.S.C. 1001(a)(1).(1) He was sentenced to four

months imprisonment, which was stayed pending this appeal. On appeal, Shaw

challenges his conviction and sentence on the following grounds: (1) the district

court lacked subject matter jurisdiction over his prosecution under 18 U.S.C. §

1001 because 42 U.S.C. 7413(c) is the exclusive means by which the

Government may prosecute the making of a false statement on a form required by

the Clean Air Act (CAA), (2) his prosecution under 18 U.S.C. 1001 was barred

by the five year statute of limitations, (3) the Government failed to show he had a

legal duty to disclose the presence of asbestos at the refinery, and (4) the district

court erred in holding Shaw accountable under USSG §2F1.1 for the cost of the

clean up of the buried asbestos at the refinery. The Government cross-appeals,

arguing the district court erred in denying a two level enhancement to Shaw's

sentence for more than minimal planning under USSG §2F1.1(b)(2). After

briefing was completed in this matter, the United States Supreme Court decided

Blakely v. Washington, 542 U.S. 296 (2004). Shaw requested permission to file

supplemental briefing addressing Blakely, which was granted. In his

supplemental brief, Shaw argues Blakely applies to the federal sentencing

guidelines and he was sentenced in violation of the Sixth Amendment.

Exercising jurisdiction under 28 U.S.C. 1291 and 18 U.S.C. 3742(a), we

affirm Shaw's conviction but remand for resentencing.

Because of the complexity of this appeal, we divide our discussion in two--first

addressing Shaw's appeal of his conviction and then addressing all

sentencing issues.

I. Conviction

A. Factual Background

Shaw, a professional engineer, owns and operates ESCM & Associates Inc.

(ESCM), an engineering and environmental consulting firm. In 1993, EZ Serve,

one of ESCM's clients, contacted Shaw concerning the Shallow Water Refinery,

an abandoned oil refinery located near Scott City, Kansas, which EZ Serve

owned.(2) EZ Serve wished to demolish the

refinery and requested Shaw's

assistance. Shaw decided to obtain bids for the demolition. On July 15, 1993, as

part of the bidding process, Shaw escorted several metal salvage companies

through the refinery. One of those companies was Southwest Wrecking, a small

company owned by Jean Stiffler and operated by Carl and Jean Stiffler and three

of their children, Lee, Scott and Carla (the Stifflers). Also present at the walk-through were

Steve Allred and Barry Yaffe, representatives of the Yaffe

Companies, another potential bidder.

At trial, Allred and Yaffe testified that during the walk-through, they

observed materials throughout the refinery which they believed contained

asbestos. They raised these observations with Shaw. According to Yaffe and

Allred, Shaw informed them the property was clean and the materials they

observed contained calcium silicate (cellulose) not asbestos.(3) Lee Stiffler

testified Shaw informed his family at the walk-through that the property did not

contain asbestos, that the insulation throughout the refinery contained cellulose

and that the only concern was the presence of hydrocarbons, which Shaw

indicated he would help abate. Carl Stiffler testified he did not recall Shaw

making any representations concerning asbestos during the walk-through; he

stated Shaw informed the Stifflers the insulation material was cellulose.

A week after the walk-through, EZ Serve requested that ESCM purchase

the Shallow Water Refinery. Immediately thereafter, the Stifflers contacted

Shaw, informing him they wished to purchase the refinery for $50,000.

Therefore, Shaw/ESCM decided to purchase the property from EZ Serve and

immediately reconvey it to the Stifflers. ESCM purchased the property from EZ

Serve for $5,000. On August 23, 1993, ESCM sold it to the Stifflers for

$50,000. Pursuant to the terms of the sales agreement, the Stifflers agreed to pay

$20,000 at closing(4) and remit the balance

(without interest) on or before August

31, 1994.(5) The agreement also informed

the Stifflers that (1) the property may

contain asbestos, gasoline hydrocarbons, and other contaminants, (2) the property

was being sold "'AS IS,'" and (3) the Stifflers assumed "all responsibility for

complying with and/or bringing the [property] into compliance with any

environmental law or regulation." (R. Supp. Vol. I at 36.) Jean Stiffler testified

she had "complete[] trust" in Shaw and that neither she nor any of her family

members read the sales agreement before signing it.(6) (R. Vol. IV at 410.)

Therefore, she stated she never knew the agreement indicated asbestos may be on

the property and Shaw never told her or her family that asbestos may be present.

In addition to the sales agreement, Shaw wrote a letter addressed to Carla

Stiffler outlining the terms of a separate agreement between ESCM and the

Stifflers. This letter, dated August 23, 1993, stated in relevant part:

This letter also serves as an agreement by ESCM to conduct up to six site

visits to the property during the next 24 months, as deemed necessary by

[the Stifflers], to provide engineering consulting. These site visits will be

for a maximum eight hour duration each and all travel will be paid for by

ESCM. Phone consultation for engineering matters will be provided

during the 24 months following closing in regards to engineering concerns

with the demolition of the refinery; these consultations will be at no cost to

[the Stifflers].

(R. Supp. Vol. I at 38.) In conclusion, the letter stated, "We look forward to

working with you on this project." (Id.) Jean Stiffler testified she never saw this

letter. She believed, based on conversations with Shaw, that he would be the

Stifflers' consultant regarding the removal of insulation (which she believed,

based on Shaw's representations, contained cellulose) and he would complete all

necessary paperwork for them. Carl Stiffler testified Shaw told his family he

would be their "environmental consultant." (R. Vol. IV at 562.)

After closing, the Stifflers began demolishing the refinery and salvaging

the scrap metal for sale. On November 3, 1993, David Branscum from the

Kansas Department of Health and Environment (KDHE) arrived at the refinery to

inspect it. He was approached by Jean Stiffler who refused to allow him on the

property, stating she would have to contact Shaw, "their environmental guy," to

see if she could let him on the property. (Id. at 585.) Branscum left the refinery

and returned to Scott City, where he learned no Notification of Demolition and

Renovation had been filed for the refinery.(7)

Branscum returned to the refinery the next day. This time, Branscum was

met by Lee Stiffler. Branscum requested access to the refinery to photograph and

take samples of suspected asbestos materials.(8) Lee informed Branscum they

needed to contact Shaw before permitting him on the property.(9) Eventually,

Shaw was contacted by telephone; Shaw informed Branscum he could enter the

property escorted by Lee Stiffler. Accompanied by Lee, Branscum inspected the

property and took pictures. After his inspection, Branscum informed Lee there

were some compliance issues, including licensing requirements, which needed to

be addressed, and it would be in the Stifflers' best interests to cease their

demolition activities.

The next day (November 5), pursuant to the Stifflers' request, Shaw

arrived at the refinery. The Stifflers informed Shaw they needed an asbestos

inspection performed and a Notification of Demolition and Renovation submitted

to the Government. They further informed him they could not continue their

demolition of the refinery until the notification was submitted. They asked Shaw

to fill out and submit the notification for them. Based on recent training he had

received in the supervision of asbestos abatement,(10) Shaw agreed to inspect the

property and complete and submit the notification. He did not require the

Stifflers to pay him for these services. While Shaw completed the necessary

paperwork, Shaw arranged for the Stifflers to work on a demolition project in

Texas.(11)

On November 8, 1993, Shaw telephoned Alice Law, NESHAP(12) asbestos

coordinator at the Environmental Protection Agency (EPA), seeking general

information concerning the EPA's regulations. He informed her of his

qualifications and told her there was no asbestos in Area A of the Shallow Water

Refinery, only bear metal tanks and piping.(13) The next day, Law received a

Notification of Demolition and Renovation concerning the Shallow Water

Refinery. The notification, dated November 8, 1993, indicated there was no

asbestos in Area A of the refinery. Specifically, it stated: "Area 'A' consist[s]

of

bare metal carbon steel tanks. No insulation or other material to test. Cut only

bare metal carbon steel piping." (R. Vol. I at 106.) It also stated: "If unexpected

asbestos or suspected asbestos material is encountered, all work will stop and

area secured until properly abated." (Id. at 107.) The notification also indicated

demolition of Area A would begin on November 18, 1993, and end on December

31, 1994. The space designated "Signature of Owner/Operator" was signed by

"Edward A. Shaw, Agent for S.W. Wrecking." (Id.)

Accompanying the notification was a certificate of Shaw's accreditation as

a supervisor of asbestos abatement projects, a map of the refinery and a cover

letter. The cover letter, written by Shaw and dated November 8, 1993, stated in

relevant part:

On November 3, 1993, [the Stifflers] were advised by . . . David

Branscum[] that they had not filed the proper notification with your office

in regards to the demolition. They immediately halted the demolition

effort and commissioned me to conduct the proper inspection and file the

proper notifications.

As we discussed, I have inspected the facility. . . . Area A consist[s] of

only bare steel tanks and bare steel piping. There is no asbestos material in

the area to be removed. There may be asbestos containing materials in

areas B and C.

The attached notice is for demolition of Area A only. No work will be

conducted in Areas B or C at this time. I will be conducting an extensive

survey in Areas B and C, collecting samples of materials that may contain

asbestos, and forwarding them to a laboratory for analysis. After receipt of

the laboratory report, I will provide a completed asbestos survey report and

will submit notification of demolition activities and asbestos removal

abatement activities for Areas B and C.

As we discussed on the telephone, [Southwest] Wrecking is a small family

owned business and [it has] a strong desire to comply with all applicable

regulations. Our company will be working with [the Stifflers] very closely

on the remainder of this project to assist them in their compliance efforts.

(R. Supp. Vol. I at 39.)

Thereafter, Shaw informed the Stifflers they could return to work at the

Shallow Water Refinery. The Stifflers returned to the refinery based solely on

Shaw's representation that they could do so as they never received written

notification from the KDHE that they could resume their work at the refinery.

Before their return to the refinery, Shaw never informed the Stifflers there was

asbestos on the property or that they should only cut bare steel tanks and piping.

He did, however, provide them with a map delineating Areas A, B and C. He

also told them to contact him before moving from Area A to another area.

On December 9, 1993, Branscum returned to the refinery to verify the

information in the November 8, 1993 "Notification of Demolition and

Renovation." He was allowed to enter the refinery, again escorted by Lee

Stiffler. Branscum took several photographs and samples from Area A of the

refinery. Later, he submitted these samples for testing. Test results revealed the

presence of asbestos in Area A.(14)

During this December 9, 1993 visit, Branscum

did not see any evidence that the asbestos was being wetted prior to its removal.(15)

On March 3, 1994, Shaw visited the Shallow Water Refinery to take

samples. At that time, the Stifflers were beginning to move their demolition

activities from Area A to Area B. At Shaw's direction, Lee and Scott Stiffler

obtained forty-eight samples from all three areas of the refinery. Lee testified

that while he and Scott were assisting Shaw, they came across a hole they had

dug to bury insulation.(16) According to

Lee, Shaw told them they could continue

to bury the insulation because it was not asbestos.(17) Carl Stiffler testified Shaw

saw the holes filled with insulation and Jean Stiffler testified Shaw told them

they could bury the insulation. Later, Shaw submitted the samples he had

collected to a laboratory in Gainesville, Florida, for testing. Samples from Areas

B and C showed the presence of asbestos; none of the samples from Area A

tested positive for asbestos.

Based on these results, Shaw completed and filed a revised Notification of

Demolition and Renovation with the EPA. This notification, which was mailed

on June 20, 1994, and received by the EPA on June 23, 1994, indicated there was

asbestos on the property and that it would be removed using the "wet method."

(R. Vol. I at 110); see n.15, supra. This notification contained the

signature of

"C.L. Stiffler"(18) and was dated April 22,

1994. (Id.)

Accompanying the revised notification was a letter from Shaw dated June

17, 1994, stating asbestos was discovered on the property. It further stated:

We have arranged, [on] behalf of [the Stifflers], to have BFI Waste

Management haul the removed [asbestos] and place [it] in [its] landfill in

Fountain, Colorado. [The Stifflers have] indicated that they are receiving

the necessary training from Kansas for Asbestos Removal Operations and

that they will have our personnel on site as Supervisors.

We will be collecting air samples on a regular basis and submitting them

for laboratory analysis. We will also conduct field fiber screening while

the asbestos removal project is in progress.

(Id. at 108.) At trial, the parties stipulated that Shaw "never requested a contract

with BFI pertaining to the disposal of asbestos from the Shallow Water Refinery

on behalf of himself or as an agent of Carl and Jean Stiffler, doing business as

[Southwest] Wrecking, nor did he ever receive or view such a contract." (R. Vol.

III at 257.) However, Shaw did contact BFI inquiring of the cost of removing the

asbestos from the refinery and disposing of it at BFI's landfill. On May 20,

1994, BFI responded by letter to Shaw's inquiry, discussing the cost of its

services.

On September 15, 1994, Russell Brichacek, Branscum's supervisor at the

KDHE, visited the refinery. He met with Lee and Carla Stiffler and informed

them that state law required them to have an asbestos contractor's license to

perform demolition activities at a site involving asbestos. He then toured the

facility with Lee. He observed several violations of the work practice standards

for the removal of asbestos. In particular, he noticed insulation had been bagged

and stored in the bath house without having been properly wetted prior to its

removal. He was informed by Lee Stiffler that this insulation material came from

Area A. He also observed insulation debris on the ground throughout the

refinery. Brichacek took two samples from the bath house; later testing revealed

the presence of asbestos.

On March 6, 1996, Kathryn Wright, a special agent in the Criminal

Investigation Division of the EPA, was asked to investigate the violations taking

place at the Shallow Water Refinery. Shaw was initially the target of her

criminal investigation.(19) In June 1996,

Wright went to the refinery but the gate

was locked and she was unable to locate anyone on the property. Wright returned

to the property in August. Again, the gate was locked and she was unable to

locate anyone to allow her access to the property. Therefore, Wright conducted a

fly-over of the property, observing that demolition activity was being performed

at the refinery. Meanwhile, Wright attempted to contact Shaw. In October 1996,

Shaw telephoned Wright and agreed to be interviewed. Wright testified that

during their conversation, Shaw told her he had instructed the Stifflers not to

allow inspectors on the facility because it "was a refinery and anybody looking

for any violation could find it." (R. Vol. V at 701.)

On November 14, 1996, Wright and her colleague William Absher

interviewed Shaw. During the interview, Wright and Absher informed Shaw they

wished to inspect the refinery. Shaw told them he would make arrangements for

the inspection. Shaw eventually informed Wright that the EPA could inspect the

refinery on December 16, 1996.

On that day, Wright and several other individuals from the EPA arrived at

the refinery with a consent to search form.(20) Wright initially attempted to hand it

to Shaw but Shaw told her she must give it to Carl Stiffler because he owned the

property. Carl Stiffler signed the form and Wright and the other individuals were

allowed to enter and inspect the property. As a result of this inspection, the EPA

issued an emergency cease and desist order to the Stifflers, requiring them to

cease all demolition activity at the refinery.(21)

In May 1997, Brichacek returned to the property. He was met by Carl and

Jean Stiffler who accompanied him as he inspected the property. He observed

demolition activity had occurred since his last visit in September 1994; in

particular, he noticed the catalytic cracker unit (cat cracker),(22) which had been

standing during his last visit, was now laying on its side. He also noticed that

much of the insulation from the cat cracker had been knocked loose and was

scattered on the ground around it. According to Branscum, Carl Stiffler informed

him that the cat cracker had been dropped(23) a week earlier and that Shaw had told

Carl there was no asbestos on the cat cracker.(24) Brichacek took samples from the

insulation material on the cat cracker; later testing revealed the presence of

asbestos. Shortly after his visit, the KDHE issued an order citing the Stifflers

with various state law violations.

On July 9, 1997, in response to the KDHE order, Jean Stiffler wrote the

KDHE a letter requesting a hearing. In this letter, she stated, "[t]he samples we

had from the catcracker were negative." (R. Vol. IV at 427 (quotations omitted).)

Jean testified she made this statement based on a package she received from

Washington, D.C., which stated the samples from the cat cracker were negative.

She testified Shaw took those samples.

After the EPA issued the cease and desist order in December 1996, Wright

visited the refinery in June 1997 to verify whether the order was being complied

with by the Stifflers. Because no one was there to allow her access, Wright again

conducted a fly-over. She observed that the Stifflers' heavy equipment was gone.

Wright also visited the refinery in July, August and October 1997. Again, no

activity was occurring.

On August 1, 1997, an informal meeting was held between several KDHE

representatives and Carl and Jean Stiffler concerning the violations occurring at

the refinery and what the Stifflers could do to come into compliance with state

law. Shaw was present and did most of the talking on behalf of the Stifflers. On

October 31, 1997, the Stifflers received their asbestos control license. In 1998,

the Stifflers hired Dennis Shelton, an accredited asbestos project designer, to

prepare an asbestos abatement plan for the refinery, which was filed with the

KDHE. In June 1998, Brichacek visited the property for the third time.

Although abatement activities had occurred, Brichacek observed that many of the

same illegal conditions were still present.

B. Procedural Background

On June 15, 1999, Shaw and Carl and Jean Stiffler were charged by

indictment with (1) conspiracy to violate the NESHAP pertaining to asbestos in

violation of 18 U.S.C. 371 (Count I) and (2) violation of the NESHAP

pertaining to asbestos in violation of 42 U.S.C. 7413 and 18 U.S.C. 2 (Count

II). Shaw was additionally charged with engaging in a scheme to falsify, conceal

or cover up the presence of asbestos in violation of 18 U.S.C. 1001(a)(1)

(Count III) and making a false statement in violation of 18 U.S.C. 1001(a)(2)

(Count IV). On November 17, 1999, a superseding indictment was issued against

Shaw and Carl and Jean Stiffler. The superseding indictment charged Shaw with

(1) violating the NESHAP pertaining to asbestos in violation of 42 U.S.C. §

7413(c)(1) and 18 U.S.C. 2 (Count I); (2) engaging in a scheme to falsify,

conceal, or cover up the presence of asbestos in violation of 18 U.S.C. §

1001(a)(1) (Count II); (3) making a false statement in violation of 18 U.S.C. §

1001(a)(2) (Count III); and (4) illegally disposing of asbestos in violation of the

Comprehensive Environmental Response, Compensation and Liability Act

(CERCLA), 42 U.S.C. 9603, and 18 U.S.C. 2 (Count IV). The superseding

indictment charged Carl and Jean Stiffler with removing asbestos without

accreditation in violation of 15 U.S.C. 2646(a)(3) (Count V).

On March 24, 2000, the Government filed a superseding information

against Carl and Jean Stiffler, charging them with failure to notify the EPA about

the storage and disposal of asbestos at the Shallow Water Refinery, a

misdemeanor. The Stifflers entered into a plea agreement with the

Government

whereby they agreed to plead guilty to the superseding information. In exchange

for their guilty pleas and their cooperation in the Government's prosecution of

Shaw, including providing truthful testimony at his trial, the Government agreed

to recommend a two point downward adjustment to their sentences for acceptance

of responsibility and to file a motion for downward departure. It was not until

they received this bargain that the Stifflers admitted they had buried asbestos on

the property. On March 27, 2000, Carl and Jean Stiffler pled guilty; they were

eventually sentenced to one year unsupervised probation.

On March 28, 2000, Shaw proceeded to trial. At trail, he testified that

during the walk-through on July 15, 1993, he informed the Stifflers there was a

possibility the property contained asbestos. He denied ever representing that the

refinery was a clean plant. With regards to the separate agreement between

ESCM and the Stifflers (outlined in Shaw's August 23, 1993 letter to Carla

Stiffler), Shaw testified the agreement pertained to ESCM assisting the Stifflers

in the designing of riggings and the testing of any liquids discovered in the tanks

on the refinery. He stated he never agreed to be their environmental consultant

and indeed, at the time of the August 1993 agreement, he did not have any

training in asbestos abatement. He further testified he told Lee Stiffler to escort

Branscum through the refinery to allow Branscum to relate any concerns directly

to Lee and for Branscum's safety. Shaw also testified that on March 3, 1994, he

did not attempt to collect clean samples from Area A and took samples from

materials containing insulation. Shaw conceded he could have made mistakes in

sampling Area A but stated he never deliberately misled anyone concerning what

he believed was on the property. Lastly, Shaw testified he never instructed any

of the Stifflers to bury insulation.

On April 12, 2000, the jury returned its verdict, finding Shaw guilty on

Count II but not guilty on Counts I and IV. No verdict was returned on Count III

because it was charged and presented to the jury in the alternative to Count II.

During trial and after the jury's verdict, Shaw moved for a judgment of acquittal,

arguing (1) insufficient evidence demonstrating a scheme to conceal, (2) the

statute of limitations barred the prosecution of Count II, and (3) he had no duty

to report the presence of asbestos. The court rejected these arguments and denied

his motion. Shaw also filed a motion to set aside the verdict, arguing the district

court lacked subject matter jurisdiction over his prosecution under 18 U.S.C. §

1001. The court also denied this motion.

C. Discussion

Shaw attacks his conviction on three grounds: (1) the district court lacked

subject matter jurisdiction over his prosecution under 18 U.S.C. 1001 because

42 U.S.C. 7413(c) is the exclusive means by which the Government may

prosecute the making of a false statement on a form required to be filed under the

CAA, (2) his prosecution under 18 U.S.C. 1001 was barred by the five year

statute of limitations, and (3) the Government failed to present sufficient

evidence demonstrating he had a legal duty to disclose the presence of asbestos at

the refinery.

Shaw raised the latter two arguments to the district court in a motion for

judgment of acquittal. "[We] review[] a denial of a motion for judgment of

acquittal de novo, viewing the evidence in the light most favorable to the

government in determining if there is substantial evidence from which a jury

could find the defendant guilty beyond a reasonable doubt." United States v.

Austin, 231 F.3d 1278, 1283 (10th Cir. 2000). We review jurisdictional issues

and a district court's interpretation of the statute of limitations de novo. United

States v. Anderson, 319 F.3d 1218, 1219 (10th Cir. 2003) (statute of limitations);

United States v. Cuch, 79 F.3d 987, 990 (10th Cir. 1996) (jurisdiction).

1. Subject Matter Jurisdiction

The CAA, 42 U.S.C. 7401 et seq., contains a provision entitled

"Federal

Enforcement." See 42 U.S.C. 7413. Within that provision is a subsection

entitled "Criminal penalties" which states in relevant part:

(2) Any person who knowingly--

(A) makes any false material statement, representation, or

certification in, or omits material information from, or knowingly

alters, conceals, or fails to file or maintain any notice, application,

record, report, plan, or other document required pursuant to this

chapter to be either filed or maintained (whether with respect to the

requirements imposed by the Administrator or by a State);

. . .

shall, upon conviction, be punished by a fine pursuant to Title 18, or by

imprisonment for not more than 2 years, or both . . . .

42 U.S.C. 7413(c)(2)(A).

Shaw contends 42 U.S.C. 7413(c)(2)(A) is the sole and exclusive means

by which the Government may prosecute the making a false statement to the EPA

in violation of the CAA. Thus, he argues the district court lacked subject matter

jurisdiction over his prosecution under 18 U.S.C. 1001. Shaw also maintains

that because 42 U.S.C. 7413(c)(2)(A) and 18 U.S.C. 1001 proscribe the same

conduct, § 7413(c)(2)(A), the specific statute, trumps § 1001, the general statute,

unless Congressional intent demonstrates the general statute is to control. He

asserts the language of § 7413(c)(2)(A) and the legislative history of the two

statutes indicate Congress intended § 7413(c)(2)(A) to trump § 1001. Lastly, to

the extent there is any ambiguity as to which statute controls, Shaw contends the

rule of lenity requires application of § 7413(c)(2)(A) because its penalty

provision maximizes punishment at two years as opposed to five years under §

1001.

The Government maintains § 1001(a)(1) and § 7413(c)(2)(A) are two

separate statutes which criminalize different behavior--the former criminalizes a

scheme to conceal a material fact from the Government and the latter prohibits

the making of a false statement within a document required to be filed by the

EPA. It argues it was not required to choose one statute over the other and

Shaw's conduct (knowingly and willfully submitting false and fraudulent

representations to the EPA over a lengthy period of time) was prohibited by §

1001(a)(1). The Government further contends that because § 1001(a)(1) is not

ambiguous, the rule of lenity is inapplicable.

Shaw's jurisdictional argument is without merit. It is well settled that

"when an act violates more than one criminal statute, the Government may

prosecute[] under either so long as it does not discriminate against any class of

defendants." United States v. Batchelder, 442 U.S. 114, 123-24 (1979)

("Whether to prosecute and what charge to file or bring before a grand jury are

decisions that generally rest in the prosecutor's discretion."). This is true even

when one statute provides a harsher penalty. In Batchelder, the Supreme Court

was confronted with two statutes, 18 U.S.C. 922(h) and 18 U.S.C. 1202(a),

which proscribed the same conduct but which carried different statutory

maximums--five years and two years, respectively. Id. at 116-17. The

Government decided to prosecute the defendant under § 922(h) and its attendant

penalty provision, 18 U.S.C. 924(a); the defendant was sentenced to the five

year statutory maximum term of imprisonment. Id. On appeal, the Seventh

Circuit concluded the defendant's sentence was limited to the two year statutory

maximum applicable to violations of § 1202(a). Id. The Supreme Court

reversed. Id. at 118. It concluded nothing in the legislative history of §

1202(a)

(which was enacted after § 922(h) and § 924(a)) revealed Congress intended its

penalty provision to override § 924(a). Id. at 119-21. It also rejected the

application of the rule of lenity, stating § 924(a) unequivocally applies to

convictions under § 922(h). Id. at 121-22. Lastly, the Court found no

constitutional infirmity with the Government's choice to prosecute the defendant

under the statute carrying the harsher punishment. Id. at 124-25.

We addressed a similar issue in United States v. Wiles, 102 F.3d 1043

(10th Cir. 1996). There, the defendant was charged with making a false

statement to the Security and Exchange Commission (SEC) under 18 U.S.C. §

1001. Id. at 1066. On appeal, he alleged that Congress intended the Government

to prosecute the making of a false statement to the SEC under 15 U.S.C. § 78ff, a

specific provision in the Securities Exchange Act of 1934 which criminalizes the

willful making of a false or misleading statement to the SEC. Id. Thus, the

defendant argued that the making of a false statement to the SEC could not

support a conviction under § 1001. Id. We rejected this argument, holding:

"Without any express indication that Congress intended otherwise, we . . .

conclude that both § 78ff and § 1001 proscribe the making of false statements to

the SEC, and the government may prosecute such conduct under either statute."

Id. at 1067. See also United States v. Radetsky, 535 F.2d 556, 567-68

(10th Cir.

1976) (rejecting argument that the defendant should have been prosecuted under

specific statute criminalizing the making of false statements in connection with

medicare claims rather than § 1001 because there was no evidence of an intent to

make the specific statute a substitute for any part of § 1001).

The same reasoning applies here. Despite Shaw's attempt to persuade us

otherwise, we fail to discern from either the language of the CAA or its

legislative history any Congressional intent to foreclose prosecutions under §

1001 where § 7413(c)(2)(A) may also apply. Without such intent, we defer to the

Government's prosecutorial discretion.(25)

Moreover, the Government alleged

Shaw engaged in a scheme to conceal the presence of asbestos. Section

7413(c)(2)(A) of the CAA does not proscribe such conduct. Consequently,

charging Shaw under § 1001(a)(1), which does prohibit such conduct (see n.1,

supra), was proper.

2. Statute of Limitations

A five year statute of limitations applies to prosecutions under 18 U.S.C. §

1001. See 18 U.S.C. 3282 (providing a five year statute of limitations for

noncapital offenses). Shaw contends the statute of limitations began to run in

November 1993, when he submitted the original Notification of Demolition and

Renovation denying the presence of asbestos in Area A of the Shallow Water

Refinery. Because the original indictment was not filed until June 15, 1999, he

argues his prosecution under 18 U.S.C. 1001 was time-barred. He further

maintains that the Government cannot rely on the June 17, 1994 Notification of

Demolition and Renovation and accompanying letter because neither of these

documents contained false information. He alleges that at the time he made the

representations within those documents, he had been negotiating with the

Stifflers to supervise the asbestos abatement project and had made the

preliminary arrangements for BFI to remove and dispose of the asbestos at the

refinery. He also states the evidence at trial did not show he signed Carl

Stiffler's name to the notification. Indeed, he states his undisputed testimony

demonstrated he provided the Stifflers with a blank notification form and they

submitted it to him with Carl Stiffler's signature. Moreover, he argues the

Government cannot rely on the letter Jean Stiffler wrote to the KDHE in 1997

because she never testified that Shaw told her the cat cracker did not contain

asbestos. More importantly, he contends there is nothing in the record

demonstrating that Jean's conduct in 1997 should be imputed to him. Lastly,

Shaw maintains that the superseding indictment charged him with concealing the

presence of asbestos. Because the alleged false statements occurring in 1994 or

1997 concerned the removal of asbestos, not its presence, Shaw asserts the

Government cannot rely on these statements as conduct occurring within the five

years preceding the original indictment.

The Government argues Shaw's prosecution under § 1001 was not time-barred. It

asserts Shaw's ongoing scheme to defraud continued until at least June

20, 1994, but also into 1997. It points to the June 17, 1994 correspondence to

the EPA (which Shaw mailed on June 20, 1994) and the enclosed Notification of

Demolition and Renovation which contained the forged signature of "C.L.

Stiffler." It contends these documents falsely stated that the Stifflers would have

ESCM personnel on site as supervisors and that arrangements had been made

with BFI to remove and dispose of any asbestos. The Government also points to

Shaw's representation to Jean Stiffler in 1997 that the cat cracker had been tested

for asbestos and no asbestos had been found. Relying on this representation,

Jean wrote the KDHE stating the Stifflers had been informed the cat cracker did

not contain asbestos and it could be demolished.

We reject Shaw's statute of limitations argument. In criminal cases, the

statute of limitations normally begins to run when the crime is complete. United

States v. Reitmeyer, 356 F.3d 1313, 1317 (10th Cir. 2004). "A crime is complete

[when] every element in the crime occurs." Id. (quotations omitted). Here, the

superseding indictment charged Shaw with a scheme to conceal the presence of

asbestos from 1993 to 1997.(26)

Therefore, the crime was not completed and the

statute of limitations did not begin to run until this scheme was completed in

1997. United States v. Jensen, 608 F.2d 1349, 1355 (10th Cir. 1979) ("[T]he

statute of limitations is no bar if there is an ongoing scheme continuing into the

[statute of limitations] period.").(27)

Because the scheme continued into the five

years preceding the filing of the original indictment (June 15, 1999), the

indictment was timely. We also reject Shaw's argument that his conduct in 1994

and 1997 cannot be included in the scheme to conceal the presence of asbestos

because it involved the removal/disposal of asbestos, not its presence. Shaw

reads the term "presence of asbestos" in the superseding indictment too narrowly.

It is clear the Government did not seek to limit his scheme only to the

concealment of the physical presence of asbestos but also the concealment of its

improper removal and disposal. Indeed, in the superseding indictment, the

Government alleged Shaw's scheme to conceal included his preparation and

submission of the June 1994 Notification of Demolition and Renovation and

accompanying cover letter to the EPA. The documents indicated the asbestos

discovered at the refinery would be wetted, bagged and removed by BFI to its

landfill in Fountain, Colorado, and ESCM would be supervising the Stifflers'

removal of the asbestos. None of this information was true.(28) Indeed, Shaw

knew the Stifflers were burying insulation.

Even limiting Shaw's scheme to the concealment of the physical presence

of asbestos, we conclude Shaw's activities in 1994 and 1997 involved such

concealment. In November 1993, Shaw informed the EPA via the Notification of

Demolition and Renovation that Area A of the refinery did not contain asbestos,

when in fact it was riddled with asbestos. Continuing that concealment, none of

Shaw's sampling from Area A in March 1994 tested positive for asbestos.

Additionally, Shaw was aware the Stifflers were burying insulation and told Lee

Stiffler they could continue to do so. Shaw also gave the Stifflers permission to

drop the cat cracker in May 1997, which was subsequently discovered to contain

asbestos. Thereafter, the EPA ordered the Stifflers' demolition activities to cease

and the KDHE cited them for various state law violations. As a result, Jean

Stiffler wrote to the KDHE in July 1997 informing them no asbestos was present

on the cat cracker. At trial, Jean testified she based this statement on samples

Shaw took from the refinery. Therefore, contrary to Shaw's arguments, his

activities in 1994 and 1997 concerned the concealment of the presence of

asbestos.

Based on the above, we conclude the statute of limitations did not bar

Shaw's prosecution under 18 U.S.C. 1001(a)(1).

3. Duty to Disclose

Shaw argues that in order to convict him under § 1001, the Government

had to prove he had a duty to disclose the presence of asbestos to the EPA. He

states that under the EPA's regulations, only owners or operators are required to

complete and file a Notification of Demolition and Renovation and therefore only

owners or operators have a duty to disclose. Shaw contends it is undisputed that

he did not own the refinery. As to whether he was an "operator" of the facility,

he alleges the EPA's definition of operator as one who "operates, controls, or

supervises a stationary source" should be declared void for vagueness. See 42 U.S.C. 7412(a)(9). Alternatively, Shaw contends that to be an "operator," one

must be more than a mere consultant and, at a minimum, must actively participate

in the day-to-day activities of the demolition/renovation operation. He asserts the

Government's evidence at trial did not support such a finding. Specifically, he

points out he was not involved in the day-to-day operations at the refinery and

made only a few visits to the refinery over a four year period.

The Government alleges that although Shaw may not have had a duty to

report the presence of asbestos to the EPA, once he did so, he was obligated to

provide truthful information under § 1001. The Government also argues there is

no requirement under § 1001 that there be a separate statute or regulation

requiring the defendant to provide information.

Section 1001 of Title 18 encompasses two distinct offenses -- concealment

of a material fact (18 U.S.C. 1001(a)(1)) and the making of a false statement

(18 U.S.C. 1001(a)(2)).(29) Shaw

was convicted of the former. A conviction

under § 1001(a)(1), unlike that under § 1001(a)(2), requires proof that the

defendant had a legal duty to disclose the fact concealed.(30) The Government

must establish that "the law required disclosure of the information at the time the

defendant allegedly concealed it . . . ." Irwin, 654 F.2d at 679 ("[T]here can be

no criminal conviction for failure to disclose when no duty to disclose is

demonstrated."). Thus, to the extent the Government is arguing that it was not

required to prove that Shaw had a legal duty to disclose the presence of asbestos

to the EPA, it is mistaken. Indeed, the jury instructions required such a showing.

Nevertheless, the Government met its burden in this case. The "duty to

disclose" element of § 1001(a)(1) can be established by demonstrating that an

agency form required such disclosure. Kingston, 971 F.2d at 489 ("A

defendant's duty to disclose is established where a government form required a

disclosure of concealed information."). In this case, the Government presented

the jury with the November 1993 and June 1994 "Notifications of Demolition and

Renovation." These forms required disclosure of whether the demolition or

renovation project involved the removal of asbestos, the approximate amount of

asbestos, the description of the work practices to be used to prevent the emission

of asbestos, and the identity of the waste transporter and waste disposal site.

Thus, these forms created a legal duty on the one completing and submitting them

to disclose the presence of asbestos and if present, the method of abatement. It is

undisputed that Shaw completed and submitted these forms to the EPA.

Consequently, he had a legal duty to disclose the presence of asbestos. This is

true even if Shaw, as a non-owner/operator of the refinery, was not required to

complete or submit these forms to the EPA under the federal regulations. See 40 C.F.R. § 61-145(b) (requiring owners/operators to provide written notice of

demolition activity involving asbestos to the EPA). The notification form itself,

apart from the federal regulations, created a duty to disclose. Additionally,

nothing in the regulations preclude an owner/operator from having an agent

complete and submit the notification on his/her behalf.

D. Conclusion

Based on the above, we affirm Shaw's conviction. We now turn to the

parties' sentencing arguments.

II. Sentence

In Shaw's presentence investigation report (PSR), the probation officer

calculated the base offense level as 6 pursuant to USSG §2F1.1, the guideline

applicable for a violation of 18 U.S.C. 1001(a)(1).(31) The officer enhanced the

base offense level by five based on the EPA's estimate that it would cost $50,000

to clean up the asbestos improperly buried at the Shallow Water Refinery. See

USSG §2F1.1(b)(1)(F) (providing for a five level increase in the base offense

level if the "loss" was more than $40,000 but less than $70,000). The officer

also enhanced the base offense level by two levels because the offense involved

repeated acts and therefore more than minimal planning. See USSG

§2F1.1(b)(2). The probation officer further recommended a two level upward

adjustment because the offense was committed by someone with special skill.

See USSG §3B1.3. Based on a total offense level of 15 and a criminal history

category of I, the probation officer determined the sentencing guideline range

was eighteen to twenty-four months imprisonment.

Shaw filed numerous objections to the PSR. In particular, he opposed the

five level enhancement based on the "loss" exceeding $40,000, the two level

enhancement for more than minimal planning and the two level upward

adjustment because the offense was committed by someone with special skill.

Shaw also filed a motion for downward departure based on aberrant behavior.

Shaw initially appeared for sentencing on June 29, 2001, but the sentencing

hearing was continued to September 5, 2001, to allow the parties to brief the

subject matter jurisdiction issue. Ultimately, the district court imposed the five

level enhancement based on the "loss" exceeding $40,000,(32) denied the two level

enhancement for more than minimal planning, denied the two level upward

adjustment based on the offense being committed by someone with special skill

and denied the motion for downward departure based on aberrant behavior.

Based on these determinations, the district court calculated an offense level of

11. With a Criminal History Category I, the court determined the applicable

guideline range was eight to fourteen months imprisonment. The court sentenced

Shaw to four months imprisonment and two years of supervised release,

recommending that Shaw serve his four month sentence in a halfway house. As a

special condition of supervised release, the court ordered Shaw to serve four

months of home confinement. See 18 U.S.C. 3563(b)(19), 3583(d);

see also

USSG §5F1.2 ("Home detention may be imposed as a condition of probation or

supervised release, but only as a substitute for imprisonment."). The court

further ordered Shaw to pay $50,000 in restitution to the EPA.

On appeal, Shaw challenges the five level enhancement based on the "loss"

exceeding $40,000 under USSG §2F1.1(b)(1)(F) and argues he was sentenced in

violation of the Sixth Amendment under Blakely v. Washington, 542 U.S. 296

(2004). The Government cross-appeals, arguing the district court erred in

denying the two level enhancement for more than minimal planning under USSG

§2F1.1(b)(2). As we discuss next, because we conclude the district court erred in

failing to impose a two level enhancement for more than minimal planning, we

need not reach the other issues.

A. Standard of Review

The Supreme Court recently decided United States v. Booker, 125 S. Ct.

738 (2005). In Booker, the Supreme Court invalidated the mandatory-nature of

the federal sentencing guidelines. Id. at 756-57. It also altered our standard of

review, requiring us to review sentences for unreasonableness. Id. at 765-66.

However, because Shaw was sentenced prior to Booker, we apply the

pre-Booker

standard of appellate review, reviewing legal questions de novo and any factual

findings for clear error. United States v. Souser, 405 F.3d 1162, 1165 (10th Cir.

2005); United States v. Doe, 398 F.3d 1254, 1257 (10th Cir. 2005).

B. Denial of Two Level Enhancement for More than Minimal Planning

Section 2F1.1(b)(2) of the guidelines requires a two level enhancement to

the base offense level if "the offense involved [] more than minimal planning . . .

." The Commentary to §2F1.1 refers to the Commentary to §1B1.1 for the

definition of "more than minimal planning." USSG §2F1.1 comment. (n. 2). The

Commentary to §1B1.1 states:

"More than minimal planning" means more planning than is typical for

commission of the offense in a simple form. "More than minimal

planning" also exists if significant affirmative steps were taken to conceal

the offense. . . . "More than minimal planning" is deemed present in any

case involving repeated acts over a period of time, unless it is clear that

each instance was purely opportune. Consequently, this adjustment will

apply especially frequently in property offenses.

USSG §1B1.1 comment. (n. 1(f)). "[T]he . . . more than minimal planning

enhancement[] [is] designed to target criminals who engage in complicated

criminal activity because their actions are considered more blameworthy and

deserving of greater punishment than a perpetrator of a simple version of the

crime." United States v. Rice, 52 F.3d 843, 851 (10th Cir. 1995).

In its cross-appeal, the Government challenges the district court's denial of

a two level enhancement under USSG §2F1.1(b)(2) for more than minimal

planning. It contends this enhancement was appropriate because Shaw engaged

in repeated acts over a period of time, including: (1) making fraudulent written

and oral representations to the EPA in a telephone call, letter and Notification of

Demolition and Renovation in November 1993; (2) conducting a fraudulent

sampling of the refinery on March 3, 1994; (3) making fraudulent representations

to the EPA in a letter and revised Notification of Demolition and Renovation in

June 1994; (4) obtaining a false signature on the revised "Notification of

Demolition and Renovation;" and (5) representing to the Stifflers that the cat

cracker did not contain asbestos. The Government also alleges Shaw's actions

involved "more planning than is typical for commission of the offense in a simple

form." It points out that in November 1993, rather than simply informing the

EPA that there was no asbestos in Area A, Shaw "took pains" in his

correspondence to (1) include his certification as a licensed supervisor of

asbestos abatement projects, (2) advise that he had personally inspected the

premises, and (3) inform the EPA that demolition activities would stop if any

asbestos was found. (Government's Br. at 29.) The Government also refers to

the fact that Shaw then conducted a sampling of the refinery in such a way as to

confirm that no asbestos was present in Area A. It also points to Shaw's false

assurances to the EPA in 1994 that the Stifflers were complying with the

environmental regulations and ESCM was supervising their activities. Lastly, the

Government points out Shaw informed the Stifflers it was permissible to bury

insulation from Area A, thereby preventing the EPA from discovering it.

Shaw contends the district court properly denied the more than minimal

planning enhancement. He contends the March 1994 sampling, the burial of

asbestos and the June 1994 correspondence were "purely opportune" and not in

furtherance of the offense. He also contends that although his sampling in Area

A did not reveal the presence of asbestos, many of his other samples tested

positive for asbestos. Based on his sampling, he prepared a revised "Notification

of Demolition and Renovation," stating "all areas" of the facility contained

asbestos. (R. Vol. I at 109.) Therefore, he contends he was not trying to deceive

the EPA about the presence of asbestos.

A district court's decision that the defendant engaged in more than minimal

planning is reviewed for clear error. United States v. Orr, 68 F.3d 1247, 1253

(10th Cir. 1995); United States v. Williams, 966 F.2d 555, 558 (10th Cir. 1992).

"Clear error occurs . . . when we are left with the firm conviction a mistake has

been made." United States v. Lin, 410 F.3d 1187, 1192 (10th Cir. 2005).

At the initial sentencing hearing, the district court denied Shaw's objection

to the more than minimal planning enhancement, stating:

In this case it appears to me - and it is accurate - this occurred over

a

period of four years, four and a half years, started in '93 and went

into '97. . . . I am aware, of course, . . . that Mr. Shaw was

acquitted on a couple of counts as well, but the standard that we use

here in terms of whether minimal planning occurred or not is not

whether it's been proved beyond a reasonable doubt or not, but it's a

much lighter standard here. It is my sense, given the number of

contacts that Mr. Shaw had with the Stifflers, with the state and the

other persons who have been involved in this case that -- let me back

up. I think a good case could be made that there wasn't more than

minimal planning or he probably would have done a better job of

trying to cover his tracks than what he did. The more than minimal

planning, seems to me the strongest evidence, is just the period of

time that it went on and the fact that Mr. Shaw did not disengage

himself from this process and made affirmative representations with

respect to the absence of asbestos at the site and that testing had, in

fact, been done when it appears that that clearly was not the case.

I think in the circumstance, while it's a close question, that the two

point increase for more than minimal planning is appropriate, and I

am going to deny that objection . . . .

(R. Vol. VIII at 1087-88.) However, at the final sentencing hearing, the district

court reconsidered this determination and denied the more than minimal planning

enhancement. It stated:

[W]hile I think technically I was correct in dealing with [Shaw's objection

to the more than minimal planning enhancement] and upholding the two-level enhancement last

time, I'm not satisfied that maybe being technically

correct is appropriate in this matter and taking a look at what Mr. Shaw's

responsibilities actually were. I'm planning to change my ruling on that to

grant [Mr. Shaw's] objection with respect to minimal planning.

(Id. at 1123.)

The district court was correct the first time. As the Government argues,

and the district court found during the initial sentencing hearing, Shaw's offense

involved "repeated acts over a period of time." "[T]he notion of repeated acts

refers to a series of acts each of which would be criminal standing alone, rather

than referring to a crime that requires the completion of a series of steps."

United States v. Proffit, 304 F.3d 1001, 1005 (10th Cir. 2002). In order to have

"repeated acts," "there must have been more than two instances of the behavior in

question." United States v. Bridges, 50 F.3d 789, 793 (10th Cir. 1994).

The evidence at trial clearly showed that Shaw engaged in more than two

acts of concealment of the presence of asbestos (each of which would be criminal

standing alone) over a four year time span. In 1993, before Branscum's first visit

to the refinery, Shaw told the Stifflers not to allow any government inspectors on

the property. After Branscum's visit, Shaw telephoned Alice Law of the EPA,

falsely informing her no asbestos was present in Area A of the refinery. The next

day, he filed the first Notification of Demolition and Renovation and cover letter,

falsely stating he had inspected the property, no asbestos was present in Area A

and ESCM would be "working with [the Stifflers] very closely on the remainder

of [the demolition] project to assist them in their compliance efforts." (R. Supp.

Vol. I at 39.) In March 1994, Shaw conducted a fraudulent sampling of the

refinery. He also observed holes where the Stifflers had buried insulation and

told the Stifflers they could continue to bury the insulation.(33) On June 20, 1994,

Shaw submitted another cover letter and the revised Notification of Demolition

and Renovation containing the forged signature of "C.L. Stiffler." These

documents falsely indicated that the Stifflers had arranged for BFI to remove the

asbestos from the refinery and that ESCM personnel would be on site to

supervise the Stifflers' abatement activities. In 1997, the Stifflers received

Shaw's permission to drop the cat cracker. In July 1997, based on Shaw's

sampling of the cat cracker, Jean Stiffler informed the KDHE that the cat cracker

did not contain asbestos. Contrary to Shaw's arguments, we find none of the

above actions "purely opportune," that is, "spur of the moment conduct, intended

to take advantage of a sudden opportunity." See United States v. Rust, 976 F.2d

55, 57 (1st Cir. 1992). Consequently, a more than minimal planning

enhancement was warranted under the "repeated acts" provision of USSG §1B1.1

comment. (n.1(f)). We also find that Shaw's offense involved "more

planning than is typical for commission of the offense in a simple form."(34) The

proper inquiry is whether Shaw's actions "demonstrated a greater amount of

planning than [is] required" to engage in a scheme to conceal the presence of

asbestos from the EPA in its simple form. Proffit, 304 F.3d at 1006. While

Shaw's scheme to conceal the presence of asbestos could have been

accomplished merely by submitting the false "Notifications of Demolition and

Renovation" in 1993 and 1994, Shaw's conduct went beyond that. He also told

the Stifflers not to permit any government inspectors on the property, took a

fraudulent sampling of the refinery, told the Stifflers they could bury insulation

from Area A and gave the Stifflers permission to drop the cat cracker. These

actions demonstrate a level of planning in excess of the amount of planning

required to engage in a scheme to conceal the presence of asbestos in its simple

form.

The district court's reasons are insufficient for reversing its previous

determination that the offense involved more than minimal planning. It did not

explain why "being technically correct" was inappropriate in this case.

Moreover, it is unclear how "taking a look at what Mr. Shaw's responsibilities

actually were" constituted grounds for the district court reversing its prior

decision. Therefore, we conclude the court clearly erred in denying the more

than minimal planning enhancement and a remand for re-sentencing is necessary.

C Imposition of Five Level Enhancement for Loss Exceeding $40,000

and Blakely

Shaw contends the district court erred in imposing the five level

enhancement under § 2F1.1(b)(1) based on the "loss" exceeding $40,000. He

also argues his sentence violates the Sixth Amendment under Blakely. Because

we conclude this case must be remanded for re-sentencing on other grounds, we

need not address these issues. Souser, 405 F.3d at 1163 n.1; United States v.

Cano-Silva, 402 F.3d 1031, 1039 (10th Cir. 2005). However, Shaw's re-sentencing must

be conducted in light of the Supreme Court's recent decision in

Booker.

III. Conclusion

Shaw's conviction is AFFIRMED. We REMAND

this matter to the

district court with instructions to resentence him in accordance with this order

and judgment and Booker.

Entered by the Court:

Terrence L. O'Brien

United States Circuit Judge

FOOTNOTES

Click footnote number to return to corresponding location in the text.

*. This order and judgment is not binding

precedent except under the doctrines of

law of the case, res judicata and collateral estoppel. The court generally disfavors

the

citation of orders and judgments; nevertheless, an order and judgment may be cited under

the terms and conditions of 10th Cir. R. 36.3.

1. 18 U.S.C. 1001(a)(1) provides:

(a) Except as otherwise provided in this section, whoever, in any matter

within the

jurisdiction of the executive, legislative, or judicial branch of the Government of

the United States, knowingly and willfully--

(1) falsifies, conceals, or covers up by any trick, scheme, or device a

material fact .

. .

shall be fined under this title [and] imprisoned not more than 5 years . . . .

2. The Shallow Water Refinery was

abandoned in the early 1980's. It consists of

approximately eighty acres.

3. Disagreeing with Shaw's representations

concerning the presence of asbestos,

Yaffe and Allred offered EZ Serve a negative bid of $225,000-$250,000 to demolish the

refinery. They believed they could sell the scrap metal on the property for $500,000.

However, they calculated it would require $225,000-$250,000 to demolish the refinery

and $225,000-$250,000 to remove the asbestos and hydrocarbons. Thus, in order to

realize a profit, Yaffe and Allred's bid required EZ Serve to pay for abatement.

4. The Stifflers obtained the $20,000 down

payment with a bank loan. Shaw

assisted them in securing the loan by writing a letter to the bank estimating the value of

the scrap metal on the property at $725,000.

5. The Stifflers have only paid Shaw $1,000

of the $30,000 balance.

6. Jean Stiffler testified she only has an

eighth grade education and usually needs

someone to explain to her what she reads.

7. Federal regulations require an owner or

operator of a demolition or renovation

activity involving the presence of asbestos to provide the Environmental Protection

Agency with written notice of the intent to demolish or renovate and to update this notice

if the amount of asbestos changes by at least twenty percent. 40 C.F.R. § 61.145(a),

(b)(1),(2). This notice must be filed with the EPA at least ten days before asbestos

stripping and removal begins or demolition work commences, depending on the specific

circumstances of each project. 40 C.F.R. § 61.145 (b)(3)(I). This notice is referred to

throughout this opinion as a "Notification of Demolition and Renovation."

8. Branscum testified experience had taught

him that refineries often had asbestos-containing insulating material.

9. Both Lee and Jean Stiffler testified they

denied Branscum access to the refinery

because Shaw had told them not to let any government inspectors on the property without

contacting him first.

10. Shaw obtained accreditation as a

supervisor of asbestos abatement projects from

the Georgia Institute of Technology on October 15, 1993.

11. Lee Stiffler testified that the Texas

project involved the removal of asbestos,

which Shaw supervised. He stated Shaw required the asbestos to be wetted prior to its

removal, bagged and hauled to a landfill. He also testified Shaw required the workers to

be suited properly when handling asbestos. Lee admitted he believed the regulation of

asbestos was "overrated." (R. Vol. III at 364.)

12. NESHAP stands for National

Emissions Standards for Hazardous Air Pollutants.

These standards were established by the Environmental Protection Agency pursuant to the

CAA and specifically regulate any activity which may result in the emission of asbestos

into the atmosphere, including the disposal of asbestos. See 42 U.S.C. 7412

(b), (d)(1);

40 C.F.R. §§ 61.140 et seq.

13. The refinery was divided into three

areas -- A, B and C. Area A was referred to

as the "light product storage area" where the oil was once stored prior to processing. (R.

Vol. VI at 886.) Area B was the hot storage area and Area C was the main process area,

containing heaters and distillate columns.

14. Lee Stiffler testified that despite

numerous calls to the KDHE, his family never

received notice of the results of Branscum's sampling.

15. One asbestos-removing procedure

involves wetting the asbestos-containing

material with a water solution, removing the asbestos, sealing it in plastic bags and

disposing of it in an approved landfill.

16. Lee testified insulation was buried in

three different locations on the property.

He stated over 100 pounds of insulation was dumped in each location.

17. Lee also testified that on other visits to

the refinery, Shaw observed other holes

where insulation material had been dumped. Lee stated Shaw did not "really say a whole

lot, just carry on." (R. Vol. III at 352.)

18. It is unclear who signed "C.L. Stiffler"

to the notification. According to Jean

Stiffler, who testified she was familiar with her husband's signature, it was not Carl's

signature. Shaw also denied forging Carl's signature. According to Shaw, he left several

blank copies of the notification with Carla Stiffler and she informed him she would

ensure that one of them got signed. Apparently, the Stifflers returned two

forms, one

bearing the signature "C.L. Stiffler" and one bearing the signature "Lee Stiffler." Shaw

completed and submitted both forms but filed the form containing the "C.L. Stiffler"

signature with the EPA.

19. Later, in April 1996, Southwest

Wrecking and Carl and Jean Stiffler became

targets of Wright's investigation.

20. Jean Stiffler testified that before these

individuals arrived at the refinery, Shaw

told her and her family that they needed to "stick together," which she interpreted to mean

that they not allow themselves to be separated until they all had the same story to tell. (R.

Vol. IV at 423.)

21. During the EPA's visit, the Stifflers

were interviewed. The Stifflers stated they

had earned $150,000 from the sale of scrap metal from the refinery and estimated another

$35,000 worth of scrap metal remained on the property.

22. A catalytic cracker/cat cracker is "[a]n

oil refinery unit in which the cracking of

petroleum takes place in the presence of a catalyst." The American Heritage

Dictionary of the English Language (4th ed. 2000). The "cracking" of petroleum is

the thermal decomposition of petroleum molecules into shorter molecules to extract low-boiling

fractions such as gasoline. Id.

23. When removing asbestos from a

height, the proper procedure is to lower it, not

drop it, in order to minimize the potential for airborne release of asbestos.

24. Jean Stiffler testified they contacted

Shaw for permission prior to dropping the

cat cracker.

25. Because we find no ambiguity in either

statute, the rule of lenity does not apply.

Callanan v. United States, 364 U.S. 587, 596 (1961) (holding that the rule of lenity,

"as is

true of any guide to statutory construction, only serves as an aid for resolving an

ambiguity; it is not to be used to beget one").

26. Count II of the superseding indictment

stated the following in relevant part:

Commencing in November of 1993 . . . and continuing through September

of 1997

. . .

EDWARD A. SHAW

within the District of Kansas, did knowingly and willfully, in a matter

within the

jurisdiction of the [EPA], [] falsify, conceal or cover[] up, by a scheme, material

facts, to wit the presence of asbestos at various locations within the Shallow Water

Refinery site . . . .

(R. Vol. I at 40.) Thereafter, Count II alleged Shaw's scheme to falsify, conceal and

cover up the presence of asbestos at the Shallow Water Refinery included but was not

limited to the following acts: (1) Shaw advising the Stifflers to deny Branscum access to

the facility, (2) Shaw's November 8, 1993 letter informing the EPA he had inspected the

refinery, that Area A only consisted of bare steel tanks and piping and Area A did not

contain asbestos, (3) Shaw's submission of the November 8, 1993 Notification of

Demolition and Renovation indicating there was no asbestos-containing material in Area

A of the refinery, (4) Shaw's June 17, 1994 letter informing the EPA that ESCM had

arranged for BFI to haul and dispose of the asbestos from the refinery, (5) Shaw's filing

of the revised Notification of Demolition and Renovation bearing the purported signature

of "C.L. Stiffler" and containing false and misleading representations, (6) Shaw's

statement at the August 1, 1997 meeting between the KDHE and the Stifflers indicating

the Stifflers had contacted several environmental firms to address the problems at the

Shallow Water Refinery, and (7) Shaw's August 15, 1997 letter to the EPA and KDHE

advising of the steps the Stifflers were taking to comply with the environmental laws and

regulations.

27. This is not to be confused with the

continuing offense doctrine. In United States

v. Dunne, 324 F.3d 1158, 1166 (10th Cir. 2003), we held § 1001 is not a continuing

offense crime for statute of limitations purposes. However, the fact that § 1001 is not a

continuing offense crime is not dispositive of the statute of limitations issue because the

Government charged Shaw under § 1001's scheme provision. Id.

at 1164 (stating a

continuing offense "is not the same as a scheme or pattern of illegal conduct") (quotations

omitted).

28. Shaw attempts to minimize the falsity

of this information. He states that at the

time he made the representations in the 1994 notification and cover letter, ESCM was in

the process of negotiating with the Stifflers to provide them its services and BFI had been

contacted regarding the removal of asbestos. However, the documents state these

representations as established facts -- that ESCM had arranged for BFI to remove the

asbestos and that its personnel would be on site as supervisors.

29. 18 U.S.C. 1001(a)(2) states in

relevant part:

[W]hoever, in any matter within the jurisdiction of the executive,

legislative, or

judicial branch of the Government of the United States, knowingly and willfully ­-

. . .

(2) makes any materially false, fictitious, or fraudulent statement or

representation; . . .

shall be fined [or] imprisoned not more than 5 years . . . .

30. Compare United

States v. Kingston, 971 F.2d 481, 489 (10th Cir. 1992) (holding

that under § 1001(a)(1), the Government must prove: "1) the defendant knowingly

concealed a fact by any trick, scheme, or device; 2) the defendant acted willfully; 3) the

fact concealed was material; 4) the subject matter involved was within the jurisdiction of

a department or agency of the United States; and 5) the defendant had a legal duty to

disclose the fact concealed"), with United States v. Irwin, 654 F.2d 671, 675-76

(10th Cir.

1981) (holding that § 1001(a)(2) requires the Government to show: "(1) the defendant

made a statement; (2) the statement was false, fictitious or fraudulent as the defendant

knew; (3) the statement was made knowingly and willfully; (4) the statement was within

the jurisdiction of the federal agency; and (5) the statement was material").

31. Because Shaw was sentenced pursuant

to the 1995 edition of the United States

Sentencing Guidelines Manual, all guideline citations refer to the 1995 edition, unless

noted otherwise.

32. At sentencing, the Government

presented the testimony of Kenneth Rapplean,

the on-scene coordinator in the Super Fund Division of the EPA. He testified

approximately 510 cubic yards of asbestos was buried at the refinery and estimated it

would cost the EPA a total of $247,479 to clean it up. Based on this testimony, the

district court found that the total cost to clean up the refinery was close to a quarter of a

million dollars and therefore, the cost of remediation will "clearly" exceed $50,000. (R.

Vol. VIII at 1075.) Consequently, the court concluded a five level enhancement to the

base offense level was appropriate under USSG §2F1.1(b)(1)(F).

33. Shaw argues that none of the Stifflers

testified he told them they could bury

asbestos; rather, he contends the evidence at most consisted of him telling Jean

Stiffler

they could bury insulation. This argument is disingenuous. The evidence at trial

demonstrated Shaw told the Stifflers they could bury the insulation without any testing as

to whether the insulation contained asbestos. The evidence further showed that the

Stifflers relied on Shaw's advice concerning the removal of the insulation and Shaw

never ensured that the insulation did not contain asbestos prior to its removal. Moreover,

once Shaw learned the refinery contained asbestos, he never advised the Stifflers on how

to properly remove and dispose of it.

34. We recognize that the district court did

not address whether Shaw's offense

involved more than minimal planning based on it requiring "more planning than is typical

for commission of the offense in a simple form." Nevertheless, because the Government

raised it below as a grounds for imposing the more than minimal planning enhancement

and no additional fact-finding need be made, we address it as an additional reason the

court clearly erred in denying a more than minimal planning enhancement in this case.

Sponsored links




This document cites




See other documents that cite the same legislation

ver las páginas en versión mobile | web

ver las páginas en versión mobile | web

© Copyright 2012, vLex. All Rights Reserved.

Contents in vLex United States

Explore vLex

For Professionals

For Partners

Company